Item Title: | Award of Contract to JAM Corporation for Fire Alarm Replacement at Harding University Partnership School |
Agenda Title: | Award of Contract to JAM Corporation for Fire Alarm Replacement at Harding University Partnership School |
Background: | On May 7, 2013 the Board approved priority List 2 for the Remainder of the Measure R 2010 bond funds and confirmed projects on Priority List 1 for funds on hand. This project is scheduled to be funded from the second sale of bond funds.The engineers final design estimate for this project is $305,000 and the construction budget for this project is $325,000 with a contingency of $32,500 and an added escalation factor of $14,872 for a total of $372,372.
A mandatory pre-bid conference was held at 9:30 AM on June 11, 2013 in response to public advertisement. Eight contractors attended the pre-bid conference and bids were opened at 10:00 AM on June 15, 2013. A bid tabulation sheet is attached |
Recommendation: | The Board of Education Approve the Award of Contract to JAM Corporation for Fire Alarm Replacement at Harding University Partnership School |
Resource Person: | David J. Hetyonk, Director of Facilities & Operations |
Fiscal Impact: | $279,244 + a 10% contingency |
Funding Source: | Measure R-2010 bond funds (fund 26). |