Item Title:Approval of Change Order Number 2, Santa Barbara Junior High School Paving & Drainage Improvements Phase I
Agenda Title:Approval of Change Order Number 2, Santa Barbara Junior High School Paving & Drainage Improvements Phase I  
Background:On May 28, 2013 the Board awarded a construction contract in the amount of $625,200 to Granite Construction Company for the subject project.  This change order is for the eight items listed in the attachment.  The total construction budget for this project is $687,720    
Recommendation:That the Board of Education Approve Change Order Number 2, Santa Barbara Junior High School Paving & Drainage Improvements Phase I
Resource Person:David J. Hetyonk, Director of Facilities & Operations
Fiscal Impact:$54,028.81  
Funding Source:Measure Q 2010 bond funds (fund 27)