Item Title: | Approval of Change Order Number 2, Santa Barbara Junior High School Paving & Drainage Improvements Phase I | Agenda Title: | Approval of Change Order Number 2, Santa Barbara Junior High School Paving & Drainage Improvements Phase I | Background: | On May 28, 2013 the Board awarded a construction contract in the amount of $625,200 to Granite Construction Company for the subject project. This change order is for the eight items listed in the attachment. The total construction budget for this project is $687,720 | Recommendation: | That the Board of Education Approve Change Order Number 2, Santa Barbara Junior High School Paving & Drainage Improvements Phase I | Resource Person: | David J. Hetyonk, Director of Facilities & Operations | Fiscal Impact: | $54,028.81 | Funding Source: | Measure Q 2010 bond funds (fund 27) |
|