Item Title: | Approval of Preconstruction Services Agreement with Frank Schipper Construction Co. for Lease Lease-back Construction Delivery Method for the Roof Replacement Project at Dos Pueblos High School |
Agenda Title: | Approval of Preconstruction Services Agreement with Frank Schipper Construction Co. for Lease Lease-back Construction Delivery Method for the Roof Replacement Project at Dos Pueblos High School |
Background: | Background Subject to the Guaranteed Maximum Sum (GMS) being acceptable, TELACU Construction Management is requesting that the Board consider Frank Schipper Construction Co. as the lease Lease-back Delivery Method contractor for the Roof Replacement Project at Dos Pueblos High School.
As part of this process, a pre-construction agreement is required to allow the contractor to review the plans and specifications for value engineering and constructability. It is anticipated that this will be a summer 2014 project with construction starting prior to the end of the school year. Attached is a draft of the agreement and slight changes may be recommended by legal counsel. |
Recommendation: | The Board Approve the Preconstruction Services Agreement with Frank Schipper Construction Co. for Lease Lease-back Construction Delivery Method for the Roof Replacement Project at Dos Pueblos High School Subject to Minor Modifications Approved by the Superintendent or District’s Legal Counsel. |
Resource Person: | David J. Hetyonk, Director of Facilities & Operations |
Fiscal Impact: | Not to Exceed $12,491 |
Funding Source: | Measure Q Bond Funds (fund 27) |