Item Title: | Approval of Proposal from Santa Barbara Electrical Design for Fire Alarm System Replacement at Monroe Elementary School |
Agenda Title: | Approval of Proposal from Santa Barbara Electrical Design for Fire Alarm System Replacement at Monroe Elementary School |
Background: | On May 14, 2013 the board approved Priority List 2 for the remainder of Measure R 2010 bond funds. This project was included on the list and the district has requested the attached proposal from Santa Barbara Electrical Design. The construction budget for this project is $200,400. |
Recommendation: | The Board Approve the Proposal from Santa Barbara Electrical Design for Fire Alarm System Replacement at Monroe Elementary School |
Resource Person: | David J. Hetyonk, Director of Facilities & Operations
|
Fiscal Impact: | $23,320 |
Funding Source: | Measure R Bond Funds (fund 26) |