Item Coversheet

Santa Barbara Unified School District


Item Title:Approval of Change order No. 6 for the Santa Barbara High School Peabody Grandstand Replacement, Stadium Renovation and Site Utilities Upgrade Project, and Approval of the contract with Santa Barbara Bowl for graduation 2019. (Vizzolini)
Agenda Title:Approval of Change order No. 6 for the Santa Barbara High School Peabody Grandstand Replacement, Stadium Renovation and Site Utilities Upgrade Project, and Approval of the contract with Santa Barbara Bowl for graduation 2019. (Vizzolini)
Background:

On July 25, 2017 the Board awarded a construction contract in the amount of $28,764,392 to AMG & Associates for the subject project.

On March 12, 2019 the Board heard a report updating the status of the project which mentioned that a change order with costs associated with discovery items in the field, and a time extension for completion of the project due to rain delays and construction challenges would be presented for approval at this meeting.  The report also identified the need to hold graduation at the Santa Barbara Bowl again this year, a cost that will be covered by the project contingency budget.

The project has a current change order contingency budget of $866,140. The attached spreadsheet shows the impact of this change order and the cost of renting the Santa Barbara Bowl on the project change order contingency budget.   

 Item 2 is the cost of change order No. 6

Item 3 is the cost to rent the SB Bowl for graduation 2019

Item 6 is our contingency budget for the Peabody Grandstand Replacement Project

Item 8 is the amount we are asking the Board to approve with this agenda item

Item 10 is our remaining contingency budget for the project.

Recommendation:That the Board approve Change Order No 6 for the Santa Barbara High School Peabody Grandstand Replacement, Stadium Renovation and Site Utilities Upgrade Project, and Approval of the contract with Santa Barbara Bowl for graduation 2019
Resource Person:Steve Vizzolini, Director of Facilities & Modernization
Fiscal Impact:$202,311
Funding Source:Measure Q 2010, Measure I 2016, developer fees, State seismic funds and Foundation for Santa Barbara

ATTACHMENTS:
File Name
SBHS_Peabody_Stadium_CO_06.pdf
Santa_Barbara_Bowl_SBHS_June_5_2019.pdf
SBHS_Peabody_Stadium_Change_Order_No_6_Board_Agenda_Spreadsheet_APRIL_2019.xlsx