Item Title: | Approval of Resolution 2018/19-60 Approving Guaranteed Maximum Price, authorizing the contractor to proceed with construction, and adopting the plans and specifications for the Adams Elementary School Playground Pavement Rehabilitation Project (Vizzolini) | Agenda Title: | Approval of Resolution 2018/19-60 Approving Guaranteed Maximum Price, authorizing the contractor to proceed with construction, and adopting the plans and specifications for the Adams Elementary School Playground Pavement Rehabilitation Project (Vizzolini) | Background: | On April 2, 2019 the Board approved Shaw Contracting, Inc. as the contractor for the subject project, which was accomplished in accordance with procedures and standards outlined in Education Code section 17406.
On May 14, 2019 the Board approved Lease-leaseback contract documents between the District and Shaw Contracting, Inc.
The contractor and the district have agreed on a Guaranteed Maximum Price (GMP) for the project in the amount of $810,225. This project has a construction budget of $1,377,443, and a contingency of $137,744 | Recommendation: | That the Board Approve Resolution 2018/19-60, Approving Guaranteed Maximum Price, authorizing the contractor to proceed with construction, and adopting the plans and specifications for the Adams Elementary School Playground Pavement Rehabilitation Project. | Resource Person: | Steve Vizzolini, Director of Facilities & Modernization | Fiscal Impact: | $810,225 | Funding Source: | Measure J 2016 (fund 29) Bond funds |
|