Item Title:Acceptance of the Completed Contract for the Dos Pueblos High School Baseball Backstop Replacement Project. (Vizzolini)
Agenda Title:Acceptance of the Completed Contract for the Dos Pueblos High School Baseball Backstop Replacement Project. (Vizzolini)
Background:

On April 2, 2019, the Board awarded a contract to RSH Construction, Inc., in the amount of $801,151.00 for the subject project.

 

Pursuant to Civil Code Section 9204, a Notice of Completion must be filed within 15 days after the completion of the work or improvement.  The design architects, engineers, inspectors, and construction/project managers have inspected the project and are satisfied that all work has been completed per the contract documents.

 

To ensure the district has received all preliminary 20-day and stop notices per Civil Code Sections 9300 – 9306, retention will be held for not less than thirty-five (35) days.  In accordance with Public Contract Code Section 7107, retention will be held not more than sixty (60) days.

Recommendation:

It is recommended that the Board of Education accept the completed contract and direct staff to file the Notice of Completion with the County Recorders Office.

Resource Person:Steve Vizzolini, Director of Facilities and Modernization
Fiscal Impact:

The completed construction contract amount is $875,650.16

Funding Source:Measure I 2016 Bond funds (fund 28)